| Secretlondon, CC BY-SA 4.0, via Wikimedia Commons |
Following my previous article, which revealed that Transport for London (TfL) has paid an extra £6.5 million in new contracts to amend routes 19 and 38 and introduce route 10, new documents show that the transport body has terminated a major London Underground refurbishment.
According to notices published on the UK Government's Find a Tender website, TfL has cancelled a contract valued at £7,200,000 (including VAT) to replace around 61,140 seats for the 'S-Stock' trains on the London Underground's Sub-Surface lines.
Let's take a look at the description of the cancelled contract:
S-Stock Passenger Seat Upgrade
Reference
WS2440522969
Description
TfL are procuring the design, manufacture and supply of circa 61,140 seats for the 'S-Stock' trains. The S-Stock fleet of trains comprises of the following lines on London Underground:
- Metropolitan Line;
- District Line;
- Hammersmith and City Line; and
- Circle Line.
This contract for an estimated duration of 3 years with an option to extend for up to 24 months.
In total there is a nominal 193 trains consisting of two variants, 'S8' (59 trains circa 360 seats each) and 'S7' (133 trains circa 304 seats each).
Contract dates (estimated)
26 March 2027 to 25 March 2030
Possible extension to 25 March 2032
5 years
Description of possible extension:
It may be prudent to extend the contract by up to 24 months to allow for risks (known and unknown) to the project.
Source: UK Government Find a Tender
Had TfL not proceeded with the changes to routes 19 and 38, alongside the introduction of route 10, which would have saved £6.5 million, would it have gone ahead with upgrading the seats on the S-Stock trains instead? 🤔
I would like to extend an invite for you to follow me on X (formerly Twitter) for transport-related updates. You can find me by searching for @CLondoner92 or by clicking on the direct link to my X page here. I am also present on BlueSky and Mastodon. I look forward to connecting with you on these platforms. Thank you for your support.
According to notices published on the UK Government's Find a Tender website, TfL has cancelled a contract valued at £7,200,000 (including VAT) to replace around 61,140 seats for the 'S-Stock' trains on the London Underground's Sub-Surface lines.
Let's take a look at the description of the cancelled contract:
S-Stock Passenger Seat Upgrade
Reference
WS2440522969
Description
TfL are procuring the design, manufacture and supply of circa 61,140 seats for the 'S-Stock' trains. The S-Stock fleet of trains comprises of the following lines on London Underground:
- Metropolitan Line;
- District Line;
- Hammersmith and City Line; and
- Circle Line.
This contract for an estimated duration of 3 years with an option to extend for up to 24 months.
In total there is a nominal 193 trains consisting of two variants, 'S8' (59 trains circa 360 seats each) and 'S7' (133 trains circa 304 seats each).
Contract dates (estimated)
26 March 2027 to 25 March 2030
Possible extension to 25 March 2032
5 years
Description of possible extension:
It may be prudent to extend the contract by up to 24 months to allow for risks (known and unknown) to the project.
Source: UK Government Find a Tender
Had TfL not proceeded with the changes to routes 19 and 38, alongside the introduction of route 10, which would have saved £6.5 million, would it have gone ahead with upgrading the seats on the S-Stock trains instead? 🤔
I would like to extend an invite for you to follow me on X (formerly Twitter) for transport-related updates. You can find me by searching for @CLondoner92 or by clicking on the direct link to my X page here. I am also present on BlueSky and Mastodon. I look forward to connecting with you on these platforms. Thank you for your support.