The Funding Challenges Preventing the Original Launch Dates for the New Tube for London (2024 Stock) for the Bakerloo, Central, Piccadilly, and Waterloo & City Lines
Thursday, 25 September 2025
Transport for London reveals reason for delays to new 2024 Tube Stock for the Piccadilly line, now expected to enter service between July and December 2026
As I’ve been keeping an eye on the Freedom of Information disclosure log on the Transport for London (TfL) website, I noticed that they have published a response to a member of the public who requested information regarding delays to the 2024 Tube Stock (also known as the New Tube for London) for the Piccadilly line.
This is a follow-up to my previous article, in which I reported on delays to the DLR rolling stock B23, now expected to enter service later in 2025.
The first test train for the new Piccadilly line fleet has arrived in
— TfL (@TfL) October 16, 2024
London 🤩🚆
This train will undergo intensive testing before the new fleet starts entering passenger service by the end of next year.
Find out more 👇https://t.co/KJZWXspHNO pic.twitter.com/0ix3MkEi5c
Request ID: FOI-1609-2526
Date published: 24 September 2025
Tuesday, 14 January 2025
Interesting FOI Requests to Transport for London – Bus Lane Enforcement on Christmas Day, Update on Central Line Improvement Programme, Piccadilly Line, and More
I will be reviewing various Freedom of Information (FOI) requests that have been responded to and published by Transport for London (TfL), particularly in relation to the current situation involving the Central Line Improvement Programme (CLIP) and the new 2024 Tube Stock for the London Underground Piccadilly Line.
Actual off-peak Oyster times
Request ID: FOI-3161-2425
Date published: 14 January 2025
Wednesday, 4 December 2024
Key Insights from TfL's Freedom of Information Requests: Electric Buses, New Piccadilly Line Announcements, and Single Justice Procedure Prosecutions
Below are the key insights from Transport for London's (TfL) Freedom of Information (FOI) requests, which I found on their website.
I hope you find this information helpful.
Request ID: FOI-2649-2425
Date published: 02 December 2024
Electric Buses
Question: It has come to my attention that only a handful of Electric buses last on routes 24/7 without using Diesel or Hybrid vehicles to cover. What action will be taken to ensure that Electric buses are able to remain on routes throughout the day and night?
Thursday, 3 October 2024
The 'New Tube for London' for the Piccadilly Line Under Construction in Goole, UK, and 32 Enviro100EV Small Electric Buses for London Bus Routes 233, R1, R3, R4 and R8
![]() |
| The New Tube for London under construction and the Enviro100EV - © Siemens and Alexander Dennis |
Today (3rd October) has been big news for manufacturing in England as we see the 'New Tube for London' 2024 rolling stock for the Piccadilly line and 32 Alexander Dennis Enviro100EV small electric buses for London Bus Routes 233, R1, R3, R4 and R8.
From Siemens UK
The Secretary of State for Transport Louise Haigh and the Mayor of London attended the grand opening of the Goole Train Manufacturing Facility, a significant milestone for Siemens Mobility and the future of rail transportation in the region. Alongside the opening, Siemens Mobility announced a substantial investment of up to £40 million in a state-of-the-art Bogie Assembly and Service Centre, further solidifying its commitment to the region.
The new Bogie Assembly and Service Centre will incorporate and expand Siemens Mobility’s current capabilities to overhaul bogies from UK trains, including the 3,224 strong fleet of vehicles (572 trains) it maintains in the UK, and will also include new production lines for assembling bogies for new trains, a first for Siemens in the UK.
Thursday, 4 March 2021
TfL and Siemens Mobility Unveil Design of the New London Underground Piccadilly Line Trains
From Siemens Mobility Press Release
Transport for London (TfL) and Siemens Mobility have today unveiled the detailed design of the new generation Tube trains for the Piccadilly line, which will soon be in production to replace the existing 1970s fleet.
The trains currently running on the line have become increasingly unreliable and expensive to maintain and will be 50 years old by the time they are replaced. Despite the devastating impact that the coronavirus pandemic has had on its finances, TfL is continuing to replace these assets, meaning that from 2025, new spacious ‘Inspiro London’ trains will serve customers on the Piccadilly line, future-proofed to ensure they are suitable for many years to come.Tuesday, 10 July 2018
Strong backing for the Holborn Tube Station upgrades
Saturday, 16 June 2018
TfL awards Siemens Mobility to build 94 new trains for the Piccadilly Line
TfL ended the rollout for the three-door, two-staircase hybrid New Routemaster bus, but they have now announced that Siemens Mobility will be building 94 new trains for the London Underground Piccadilly Line.